Papers and Articles - II

  (Full paper or Selected Pages of the reports with **are attached in this section)

 

** Full Paper of No. 3 - Wu, B. “Innovative Innovations for Economical 300/450mm IC Fabricators” 2002 IEEE/SEMI ASMC April 30-May 2, 2002, Proceeding pp 150 – 155

==========================================================

 

Innovations for Economical 300/450mm IC Fabricators

 

 

Bevan P. F. Wu

Bevan Wu & Associates

2490 Cowper Street, Palo Alto, CA 94301

USA

Bevanwu@stanfordalumni.org

 

 

 

 


Abstract

The conventionally designed 300mm IC fabricator in an automated environment has many drawbacks such as: high capital outlay and high cost of ownership, long fab construction time, low flexibility for multi-product and multi-process operation, long process cycle time and high work in process.  These drawbacks have an enormous impact on the economics of a 300mm fab.  This paper proposes a new fab architecture and operational philosophy to improve the economics of 300mm/450mm fabs.  The new fab architecture and design will reduce capital outlay and fab construction time by 50%, increase equipment utilization by 100%, reduce COO by 30%, and reduce both process cycle time and work in process by at least 30%, and cut annual operating expense by 30%.  Integral to this new approach is the cooperative alignment of IC makers and equipment suppliers throughout the equipment and fab life cycle.  By closely working together, both will reap the economic rewards.  

Keywords

IC Manufacturing Economics   IC Fabricator Architecture   IC Fab Design   Semiconductor Equipment Design   Cost of Ownership   IC Fab Operations

1.        Introduction

There are nine 300mm fabs in existence in the world today.  These fabs cost billions of dollars to build; it is therefore imperative for these fabs to run constantly and smoothly to stay ahead of their depreciation curve.  This means that a 300mm fab must be reliable, flexible, and fully automated requiring minimum human intervention.  Yet today’s 300mm fabs are not necessarily more reliable or flexible than 200mm fabs, because the 300mm fabs employs a similar equipment and fab design as that of 200mm fabs, only larger in size.  In addition, the automation of 300mm fabs also requires more manpower in order to maintain both equipment and the systems in operation.  A staffing level of 700 plus for a 300mm fab is not unusual.  In an environment of ever changing market demand versus the capacity planning of IC manufacturers/foundries, both the IC manufacturers and the equipment suppliers are paying high prices caused by the mismatch of forecast versus actual capacity demand.  In the fourth quarter of 2001 there was 40% more fab capacity than actual demand, which means many fabs are running way behind their depreciation curve.  This paper proposes a new innovative fab design and operational approach for 300mm and 450mm IC fabs to mitigate the above situation.  It calls for close cooperation among IC manufacturers and equipment suppliers to literally think outside of the box. The payoff is great. A joint innovative effort could reduce capital outlay and fab construction time by 50%, increase equipment utilization by 100%, reduce COO by 30%, reduce both process cycle time and work in process by at least 30%, cutting annual operating costs by 30%, By standardizing common equipment and facility interfaces as well as physical and software protocols, the lifetime of a fab may be extended from the 300mm to the 450mm generation. This innovative approach will enable the semiconductor industry to adapt to future steep demand variations in the world market place. 

2. Conventional 300mm Fab Drawbacks

The conventional 300mm fab design is similar to that of a 200mm fab with an automated material handling system (AMHS) housed in an enlarged ballroom encased in a 3 or 4 level structure.  The drawbacks are:

High Capital Cost: Unless sufficient clean room space and facilities are constructed for the current and expected future capacity demands of the fab initially, it will be costly to add additional capacity afterwards.  That means extremely high capital outlay for fab construction to the tune of $1.5B to $2.0B.  

Long Fab Construction Time: The fab building time ranges from 18 to 24 months because of the sequential nature of building construction, facilities and equipment installation activities.

Low Flexibility: The physical layout in the clean room area constrains the fab flexibility for multi-product and multi-process operation. The slow AMHS speed caused by vibration and contamination concerns in the ballroom also limits fab flexibility. Any modifications in equipment or adaptation of new process would risk the interruption of fab operation.

Long Cycle Time and High WIP: Short MTTF and long MTTR of semiconductor equipment together with the slow AMHS speed cause a long production cycle time and a large amount of work in process (WIP) stored in expensive stockers.

High COO: Semiconductor equipment by its nature has a short lifetime and is subject to the fast change of technologies; it is difficult for their reliability to equal that of mature industrial equipment.  This intrinsic low reliability of semiconductor equipment contributes to the low average fab equipment utilization around 35% in 200mm fabs, and the average equipment utilization of a conventional 300mm fab is not likely to exceed that of the 200mm ones.

Short Fab Life Cycle: Despite the great progress made in SEMI standardization efforts in 300mm equipment and fab architecture, it is difficult to design a conventional fab to cover both 300mm and 450mm generation wafer sizes in a single fab’s lifetime.

  1. Proposed Innovative Fab Design

The proposed new IC fab design consists of hundreds of transportable, environmentally controlled process modules placed on a fab superstructure with a facilities supply system installed in the superstructure instead of the conventional brick and mortar fab building.  The process modules are connected by an independent automated rapid material transit system.  Figure 1. shows an overview of a fab designed with the new architecture. A pancake shaped superstructure houses hundreds of rectangular shaped process modules and five dome-shaped control centers for accommodating operating personnel. The modular units are arranged in 3 concentric rings in the super-structure.  The pancake shaped super-structure shown in Figure 2 serves as the main fab structure for foundation and facility support of the whole IC fab. The construction of this super-structure and the facility support system can be built on-site parallel to the construction of the process modules offsite at equipment supplier locations. The two construction activities do not interfere each other as often happens in the case of the conventionally designed fabs.  This will cut overall construction time from the present minimum of 18 months to 9 months.  It means the new Fab will bring IC product to the market 9 months earlier than a conventional fab.  

 

 

Figure 1: New Architecture Fab Design Overview

 

 

 

Figure 2: Super-structure of the New Fab Design

 

Figure 3 shows the independent rapid material transport system (which consists of four monorail rings) sandwiched between rings of process modules on the super-structure. Figure 4 shows one of the many multi-pod carriers mounted on the monorail.  This rapid transportation system moves wafer pods (FOUPs) among process modules.  It is like the inter-bay transportation of a conventional 300mm fab.  Because this rapid material transport system is built on foundations separated from the main fab super- structure, it can operate at high speed to achieve short cycle time without generating vibrations in the modular process areas.  The fast inter-module transportation combined with the granular modular manufacturing unit form a powerful, flexible IC Fab that meets the requirements for multi-product and multi-process operation.  The fab also can handle fast process routing changes as well as process equipment modifications to extend fab life. 

Monorails

 
 


Figure 3: Rapid material transport system (4 rings of monorail on their support posts)

Environ’t chamber

 

FOUPS

 
 

 


Figure 4: A monorail multi-pod carrier

 

Figure 5 shows the schematic of a process module; its profile resembles the conventional 3-level fab design.  Each module is made of an upper sub-module and a lower sub-module connected at the equipment floor level.  The upper sub-module consists of fan-filter units for environment control; an overhead material transportation serves as an intra-module (intra-bay) wafer or FOUP mover.  The bottom floor of the upper sub-module is made of standard clean room floor plates placed on steel beams.  Each process module can accept 3 or 4 pieces of processing or metrology equipment.  This upper sub-module is removable by disconnecting the supply/facility piping through quick connectors from the lower sub-module for fast replacement of a calibrated standby or modified upper sub-module.  This design feature is to shorten fab downtime due to major equipment repair or modification. The lower sub-module contains the supply lines (gas, chemical, water, and electricity) and support equipment such as pumps or electrical boxes.  They are semi-permanently connected to the facility supply network housed by the fab super-structure.  The unit construction cost of the manufacturing module is estimated to be 2/3 of that of a conventional IC Fab of equal floor space with the same environment clean class.  The operating energy cost of the new IC Fab design is estimated to be 2/3 of that of a conventional fab of the same production capacity because of the smaller clean modular manufacturing area required.  The transportable process modules are designed to take advantage of the well-developed worldwide container transportation infrastructures. The manufacturing module itself is both the equipment-shipping containers as well as the manufacturing environment in which the equipment is housed.  They can be constructed and loaded at the equipment supplier’s location for shipment to the Fab construction site, and can be placed on the super-structure connected to the facility system.  It saves equipment installation and calibration time as well as shipping costs. Prototype process modules have been built and tested. Results show that the modules can be installed on a fab within 5 hours [1]. Fully loaded modules of a similar design were shipped across the ocean to their fab site; and all installed equipment in those modules started functioning properly when powered on in their fab [2]. 

Facility supply system

 

Interface to monorail

 

Upper sub-module

 

Lower sub-module

 

Figure 5:Schematic of a transportable process module

4. Advantages of the New Fab Design

The proposed new fab design with transportable, manufacturing modules addresses most of the drawbacks of the conventional 300mm fab with economical advantages, yet the new fab design requires no scheduled technology invention.  All employed technologies are available with proven industrial reliability and infrastructure.  The new fab design advantages address each of the conventional 300mm fab drawbacks as follows:

High Capital Cost Reduction: The new fab design enables both the fab superstructure including facilities and the manufacturing modules to be constructed in parallel. The number of modules for the fab can be tailored for the necessary capacity required by the market by the time of installation of the modules at the fab site. The new fab design and operation paradigm provides leasing options that may not have previously existed. Instead of owning the equipment outright, which accounts for more than 70% of a fab’s cost, the IC Maker can lease the equipment and sub-contract total maintenance of the modules and equipments to their respective supplier. Thus the savings on both initial capital investment and interest expenses can easily be reduced by 50% with respect to that of conventional 300mm fab. By properly structuring the charges there will be a steady flow of income from equipment leasing and contracted maintenance for the suppliers to pursue profitable new product development and production. It is a win-win proposal for both the makers and suppliers.

Reduction of Long Fab Construction Time: The conventional 300mm fab building time ranges from 18 to 24 months due to the sequential nature of fab construction. The new fab design reduces construction time by 9 to 12 months through parallel processing of its building activities. The construction of manufacturing modules and the building of infrastructure and facilities are progressing simultaneously without interference from each other. In addition to capital savings, the Maker reaps a huge economic and strategic advantage by getting his product to the market 9 to 12 months ahead of his competitors.

Improved Fab Flexibility: The new modularized fab with high speed AMHS provides an ideal agile manufacturing system for multi-product and multi-process operation. Any substantial modifications in equipment or adaptations of a new process will only affect one module without risking interruption of the entire fab operation. The modular architecture also reduces the risks of environmental, health and safety exposures of a conventional fab. Furthermore, R/D works of new process/equipment can be completed in a real manufacturing module offsite. After completion of R/D, the module can be delivered to the site and incorporated into the fab. For example, the CMP environment contamination concerns present during adaptation to a conventional fab would be greatly reduced by the modular fab architecture.

Short Cycle Time and Low WIP: The combination of rapid independent AMHS among modules and the short intra-module wafer mover facilities within each module provides the new fab with a high speed multi-path AMHS. Optimized product routings from the fab manufacturing execution system can easily be carried out by the multi-path agile AMHS.  Short MTTR is achieved by replacing out of order module with calibrated standby unit.  This enables the fab to run with just local buffer storage on equipment instead of large costly stockers.  Since up to 90% of the wafer cycle is in stocker waiting time, the elimination of stockers with fast, flexible AMHS and local equipment buffers will cut production cycle time by at least 30%.  Low WIP is a natural consequence of shorter cycle time and the elimination of large expensive stockers in a conventional fab.

Low COO and Fab Operation Expenses: The new fab design replaces the traditional brick and mortar fab with modules on a superstructure; its estimated cost is 2/3 of that of a conventional fab with the same capacity.  The new fab design also recognizes the intrinsic limited nature of semiconductor equipment by not requesting unreachable equipment reliability in its planning. Instead, the fab’s modular, quick replacement capability will improve average fab equipment utilization from 35% to 70%.  By leasing process modules populated with equipment and sub-contracting out equipment maintenance to the suppliers, the IC maker does not have to hire an expansive team of equipment maintenance experts.  All these advantages result in the reduction of COO by 30%.  The new 300mm equipment is highly automated requiring minimum human intervention to the operation of equipment installed in process modules.  By eliminating the main source of contamination resulting from human operation the clean environment inside the module will need only very little energy to maintain its cleanness.  The overall fab energy cost can easily be reduced by 30% from that of an equivalent conventional ballroom fab.  

Long Fab Life Cycle: In the new fab design the sub-systems like inter-module AMHS and facilities support can be designed to accommodate both 300mm and 450mm wafers with small incremental fab costs.  The manufacturing modules can also be designed to accommodate both wafer sizes at a moderate cost.  The key to a successful implementation of a long life fab design is to accelerate the great progress made in SEMI standardization activities in 300mm wafer fabs.  Not only should this activity be expanded to both 300/450mm wafers, but the hardware and software interfaces for equipment and facilities should also be agreed upon and adopted by all suppliers.   Most large wafer process steps will be done in single wafer chamber; a family of standard facility backbones can be designed to accommodate both size wafers with similar physical interfaces and reusable supporting software.  Because of the decentralized design and building process, it is relatively easy to implement a long fab life strategy in a modular fab, compared to designing for both 300mm and 450mm wafer sizes in a conventional 300mm fab environment.  If a fab’s life can be extended to two generations of wafer size, the cost of manufacturing would be reduced by almost half.

All the drawbacks of a conventional 300mm fab mentioned in section 2 have been addressed with substantial economical savings by the proposed new fab design and operation philosophy. 

5. Discussions

In the era of 300mm and 450mm Silicon wafer manufacturing large process equipment manufacturers will play a pivotal role in the standardization of process equipment and its interface design. This in turn, will affect the fab design.  The users are left to tailor their individual process variations through operational parameters. Standardization in equipment does not diminish industrial competition, since more and more semiconductor product differentiation will be based mainly on product design.  A winner product has the best intellectual design content to meet the market demand with the most economical manufacturing cost.  The 30% to 50% manufacturing cost advantage offered by the new fab design certainly is a competitive tool for any IC maker.  Now is the time for IC makers and equipment suppliers to think outside of the box by jointly working out a coherent program to implement the new fab concept based on SEMI standardization to assure the semiconductor industry a continuous growth along Moore’s curve without steep upheavals resulting from demand and capacity mismatch.  The modular fab concept has been considered by R/D laboratories and economically conscious semiconductor manufacturers worldwide [3].  A R/D project was carried out in the Industrial Technology Research Institute (ITRI) Taiwan from 1997 through 1998 to evaluate the feasibility of the new fab design with the manufacturing module concept. The feasibility of the proposed architecture and module design was validated by experimental results [1].  Figure 6 shows the prototype-manufacturing module of the new fab design on ITRI campus. The top 2 sections belong to the upper sub-module, and the bottom section belongs to the lower sub-module.  The 3 module sections were fabricated off site, and were shipped to ITRI via truck. The whole module was assembled in 5 hours. The module reached class 0.1 environments, and had a recovery time of less than 5 minutes after the environment was contaminated.  An Applied Material thin-film deposition system donated by TSMC was installed in the module.  In the same time period a Swiss company delivered modular semiconductor processing units based on a similar design concept to its customer’s great satisfaction [2].

Figure 6: A Transportable Semiconductor Processing   Module on ITRI campus, Hsinchu, Taiwan

6. Conclusions

This paper proposes a new fab architecture and operational philosophy to improve the economics of 300mm/450mm fabs.  The new fab architecture and design will reduce capital outlay and fab construction time by 50%, increase equipment utilization by 100%, reduce COO by 30%, and the reduction of both process cycle time and work in process by at least 30%, cutting annual operating expense by 30%.  Early feasibility studies showed promising results. This new fab design and its new operational approach require both the IC makers and the equipment suppliers to closely cooperate throughout the equipment and fab life cycle to reap mutual economic benefits.  It is believed that this fab design will assure the world semiconductor industry a continuous growth along the Moore’s curve without steep upheavals resulting from demand and capacity mismatch. 

References

[1]. Bevan P. Wu: Modular Clean Room for Effective Integrated Circuit Manufacturing – MIRL/ERL Joint Accomplishment, ITRI Today, No. 16, Spring (1999) pp. 1-4, Industrial Technology Research Institute, Hsinchu, Taiwan, R.O. C.

[2]. Private communications

[3]. Kishore Potti: Survey of 300mm Wafer Fab Designs, Semiconductor Fabtech, Edition 6, May (1997)  pp. 101-106   

 

 

**Selected pages of  No. 18 - Wu, B. "The First Automated Semiconductor Manufacturing System in the Industry - The FMS Feasibility Line"  IBM Research Report RC 14203, November 28, 1988